Moray East Grout Logistics

Project Scope

Handling of 14000mt of grout to feed to the jacket grouting vessel Boa Sub C

Project Details

Year: 2020
Value: £1.5M
Client: Deme Offshore

Marine Logistics

Discharging of 600 cronos of grout from inward bound coaster vessels, transporting to storage feeder port storage area

Quayside Support

Filling grout silos on 24/7 basis for arrival of dedicated grouting vessel Boa Sub C Backloading empty Cronos tanks to coaster vessel

All lifting equipment, transport, cranes, lifting teams, RAMs and documentation